施工事例‎ > ‎

Downtown Line Stage 2; C913

Owner : Land Transport Authority 
General contractor : GS Engineering & Constr. Corp. (Tuksu Eng. & Construction, Ltd)
Application : Soft-Eye
FiReP Solution : FRP reinforcement for TBM break-through
Construction date : 06/2010
Excavation method : NATM 
Products : FiReP Rebar straight d=40mm, d=24mm, FiReP Rebar helix d=22mm
General information : Cashew駅にSoft-Eyeが設置され、4台のTBMで掘削されました。

Jobsite Photos